Redirecting to default login..
Personnel
operating personnel
Personal protective equipment
➜ Protective work clothing
➜ Safety shoes
➜ High visibility vest
➜ Protective gloves
➜ Industrial safety helmet
➜ Hearing protection
Initial commissioning
Initial commissioning is carried out by the manufacturer. The handover of the machine to the customer is documented in an instruction log, and the limiter plates supplied must be fitted before the machine is commissioned for the first time with a limiter.
Recommissioning
Before recommissioning, carry out the measures “After storage” see “Storing the machine”.
Switch on the machine
When the machine is in working position, it can be switched on.
1. Ensure that there are no persons or materials in the danger zone.
2. Ensure that all daily checks have been carried out.
3. Switch on the battery isolator switch.
4. Switch on the machine; select the operating mode and carry out further steps.
The machine is now ready for the shredding process.